Resource Leveling and Crew Flow
Leveling respects resource limits and adjusts dates accordingly; smoothing keeps dates but flattens demand where float exists. Use leveling during planning to avoid impossible stacks, then smooth during execution to reduce overtime spikes. Document impacts so leadership understands the realistic path to milestone success.
Resource Leveling and Crew Flow
For hotels, rail segments, or housing, use Line of Balance to set crew rates and spacing. A corridor project improved productivity 18% by staggering crews with a consistent takt time and clear buffers. Visualizing crew lines prevented stacking trades in the same zone and reduced rework disputes.